Funded by the World Bank and under the supervision of Ministry for Agriculture.
This project involves developing the pipe network and 138 pump stations to increase the efficiency of irrigation in the region.
This project served 200,000 local residents and decreased water waste in this area by 22%.
The contract value is $6.8M
The project was completed on 31/12/2017.
Finish Date | 31/12/2017 |
Client | Ministry of Agriculture |
Consultant | Saleh & Hegab |
Location | Kafr El Sheikh |